Construction Update

Friday, June 24th, 2016

Grading has begun on the west and east sides of the Brentwood Branch. The west side grading is making way for the expanded reading area. The east side grading (not pictured) will make way for a convenient drive-through lane. Patrons will be able to pull through it from south to north and exit through the east drive onto Seminole Street.  Workers have removed the west driveway entrance off Seminole Street permanently. A crew will add a new driveway off of Brentwood Blvd. as part of the project. Demolition on the inside continues, and workers have begun the layout for interior walls. Stay tuned for more as we ReNew Brentwood!

Library BWD CATLibrary BWD front grading 3Library BWD front grading 1